the Ridge: week 7
Last week the deck floor was build, with the EPDM waterproofing membrane installed, more fill has been brought in for under the garage slab and foundation back fill (now the…
Last week the deck floor was build, with the EPDM waterproofing membrane installed, more fill has been brought in for under the garage slab and foundation back fill (now the…
Today the crew finished up the subfloor of the main floor. The stair well. Shawn applies glue to the top of I-joists. Shawn (the other one) nails down the plywood.…
Yesterday was another big day on the Ridge building site: the crew installed the main floor/deck beams!