the Ridge: week 21
The installation of metal siding is underway! Check out the metallic (‘weathered zinc’) corrugated metal siding panels: I can’t wait until the red metal siding goes on!
Posted in the Ridge
Leave a comment
the Ridge: week 20
After a well-deserved christmas break, a skeleton carpentry crew is back at work, while the insulators continue filling in the wall cavities with blown-in cellulose. Blowing in cellulose Recycling spilled cellulose Clear cedar siding on the back
the Ridge: week 18/19
The week before last (week 18), ‘Quality Interior Kontracting’ started to install blown-in cellulose. This insulation, made from recycled paper, is blown ‘wet’ into the wall cavities – filling all nooks and crannies. Then it will have some time to dry … Continue reading
Posted in Projects, the Ridge
2 Comments
the Ridge: week 17
Yahoo!, the roof is on!! In the meantime, the electrician is busy wiring; the mechanical ducting is largely installed, including the HRV, the air to air heat exchanger and the electrical furnace; all plumbing is roughed in and the carpenters … Continue reading
Posted in Projects, the Ridge
2 Comments
the Ridge: week 12
Sorry folks, I’ve been off the map for a little while and neglecting to post new pictures of the house construction in progress… Just been so busy! All roofs have peel & stick on and are waterproof! The view from the … Continue reading
Posted in Projects, the Ridge
Leave a comment
the Ridge: week 11
Autumn is really upon us now – it has been raining for a week straight – and the crew continues work on the roof. Garage & bed room wings covered with T&G, insulation, strapping & plywood. Garage has peel & stick, … Continue reading
Posted in Projects, the Ridge
Leave a comment
the Ridge: week 10
The race is on now to get the roof on before winter sets in … Chris hands a board up to Shawn. Note the stack of pre-stained T&G inside. White washed pine (pre-painted) against fir rafters. Early in the week, … Continue reading
Posted in Projects, the Ridge
Leave a comment
The Ridge: roof framing
Saturday the remaining roof rafters were installed. Here follows a selection of the 196 (!) pictures I snapped during raising. I thought of making a smaller selection, but these really show off the process of the raising and the details … Continue reading
Posted in Projects, the Ridge
Leave a comment
the Ridge: week 9
This week the crew put up the remaining bearing walls, installed the outrigger beams and the rafters of the garage. Stay tuned, today the rest of the roof rafters will be installed!
Posted in the Ridge
Leave a comment
the Ridge: materials
When the glue-lam beams for the deck needed to be installed a few weeks ago, Tom Thompson, the painter wanted to use Bona, an oil finish with chemical ingredients, but I wanted to use a more natural finish. So we … Continue reading
Posted in Projects, the Ridge
Leave a comment