the Ridge: week 20
After a well-deserved christmas break, a skeleton carpentry crew is back at work, while the…
the Ridge: week 18/19
The week before last (week 18), 'Quality Interior Kontracting' started to install blown-in cellulose. This…
the Ridge: week 17
Yahoo!, the roof is on!! In the meantime, the electrician is busy wiring; the mechanical…
the Ridge: week 16
This week the roofers started installation of the metal roofing. Standing seam metal roofing Steel…
the Ridge: week 14
All the doors and windows (manufactured by Innotech) are installed now and the garage slab…
Wooden skyscrapers in BC
Vancouver architect Michael Green proposes to build skyscrapers with engineered wood for the structure, floors…
the Ridge: week 13
Well, we got a little touch of winter last week: temperatures below freezing and a…
the Ridge: week 12
Sorry folks, I've been off the map for a little while and neglecting to post…
the Ridge: week 11
Autumn is really upon us now - it has been raining for a week straight…
the Ridge: week 10
The race is on now to get the roof on before winter sets in ...…
The Ridge: roof framing
Saturday the remaining roof rafters were installed. Here follows a selection of the 196 (!)…